Tests on electrical system

We perform commissioning tests of the electric system of Wind farm. Commissiong tests are required to show that electrical system is ready and safe for operation. They should be done after final adjustments and most of the tests are included in manufacturer`s standard documentation.

Closeup of male electrician examining fusebox with multimeter probe

Commissioning tests of electrical part of Wind power plant consist of:

  • Demonstration of satisfactory operation of power measurement equipment
  • Function tests of the relay protection and verification of settings.
  • Demonstration of satisfactory operation of control equipment (Siemens Sicam control equipment).
  • Demonstration of satisfactory operation of 33 kV cubicles.
  • Demonstration of satisfactory operation of the diesel generator.
  • Demonstration of satisfactory operation of the transformer cooling equipment.
  • 24 hours voltage test on the cables.