WTG Test on Completion

Test on Completion (ToC) can be done only after Commisioning tests are finished and validated.

It includes:

  • ToC for single (individual) WTG
  • ToC for complete Wind Power Plant (WPP)


ToC for single WTG

This test requires generator to be in operation for 240 hours, 150 hours if which should be generation time (wind generator gives power to the grid). Its allowed to have 3 generator faluts during whole test, but its not alowed to have any mistake during last 100 hours.

ToC for Wind Power Plant

This test requires wind power plant to be in operation for 200 hours, 150 hours if which should be generation time.