MV switchgear connection at substation platform

All the incomming cables from the wind towers are gathered, switched and protected inside MV switchgear. We provide cable connecition of switchgears.

We perform power cable connection it the following steps:

  1. Dismantle the flor plates of the cable compartments. Remove the cable bushings from the floor plates.
  2. Lay power cables to the panels according to the project.
  3. Make sure that the phase sequenses of the cables are correct
  4. Slide the cable bushings over the cables
  5. Connect the cable connectors to the cables according to
    the manufacturer’s instructions.
  6. Check the cable sockets and/or the outer cones
    for damage.
  7. Remove surplus or dirty grease or soiling from the cable
    sockets and/or the outer cones with a soft, clean, non-fraying
    cloth.